What does Cost As an Independent Variable (CAIV) refer to?

Study for the Army Acquisition Exam 1. Enhance your knowledge with multiple choice questions, flashcards, and detailed explanations. Get ready to excel on your exam!

Cost As an Independent Variable (CAIV) is specifically a strategy used in the acquisition process that emphasizes cost as a fundamental management variable. This approach involves integrating the cost element into the decision-making processes from the very beginning of a project, rather than treating it as just another constraint to be factored in later. By considering cost independently, it allows for a more dynamic response to changing project requirements and facilitates better trade-offs between performance, schedule, and cost.

This strategy encourages program managers to prioritize cost considerations throughout the entire lifecycle of the system, ensuring that budget constraints do not overly compromise the functionality and performance of the acquisition. It emphasizes the notion that cost should not be an afterthought but a core aspect of design and planning in acquisition programs. In this way, CAIV plays a crucial role in achieving a balance between cost goals and operational effectiveness.

While other options discuss aspects of project management and budgeting, they do not capture the specific framework and philosophy of CAIV as it relates to managing cost with a primary focus in the acquisition context.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy