What is the basis for developing the Contract WBS?

Study for the Army Acquisition Exam 1. Enhance your knowledge with multiple choice questions, flashcards, and detailed explanations. Get ready to excel on your exam!

The basis for developing the Contract Work Breakdown Structure (WBS) is the Program WBS. The Program WBS serves as a comprehensive framework that outlines the scope of work for the entire program. It breaks down the project into its constituent components, ensuring that all elements necessary for successful completion are accounted for.

Using the Program WBS as the foundation for the Contract WBS helps to maintain consistency and alignment with the overall goals and structures set by the program. This systematic breakdown allows for better management of tasks, resources, and timelines while providing clear visibility into responsibilities and deliverables associated with the contract.

In contrast, task assignments, federal regulations, and project objectives may influence specific aspects of the Contract WBS but do not serve as its primary foundation. Task assignments focus on specific duties within a project, while regulations ensure compliance with legal and policy requirements but do not determine the overall structure. Project objectives outline what the project aims to achieve but are not designed to provide a detailed work breakdown.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy